Sunday, July 27, 2008

Project Timeline

Timeline/Dates
27/07 -
Develop a draft version of the website, from what had been discussed at both
our meetings.

28/07 -
Begin transferring the design into Wordpress.

29/07 -
Continue developing the site and fix problems.

30/07 -
Meet with Community group to review and critique the draft.
Get more ideas for further development.

31/07 -
Start on the final design.

01/08 -
Mid Challenge review and continues the webpage development.

05/08 -
Final meeting with Community group to review the final outcome.

06/08 -
Debug and fix up any problem that may occurred. Add additional features if.
time allow.